EDIT PROJECT STANDARD COST RATE SHEET – ADDING NEW PROJECT STANDARD COST RATE RULE TO PROJECT STANDARD COST RATE SHEET
Edit Project Standard Cost Rate Sheet - Adding New Project Standard Cost Rate Rule to Project Standard Cost Rate Sheet
Overview:
This document is a guide for Finance and Financial Managers to assist them in adding the newly created Project Cost Rate rules to the Standard Cost Rate Sheet. This process is only for Union Craft profiles, all other profiles and rates are set up on the Resource Plans.
Access Workday from the SwinNet “Go To” drop down menu or Workday Desktop Icon
STEP 1: Once in Workday, navigate to “Edit Project Standard Cost Rate Sheet”
STEP 2: Name - Select “Swinerton Standard Cost Rate Sheet”
STEP 3: Effective Date - Accept 01/01/2017 default
STEP 4: Once the screen populates, click the “+” sign to add a row
STEP 5: On the blank row, search and select the Project Standard Cost Rate Rule you created
STEP 6: Once the rule has been added, scroll to the left and add the Standard Cost Rate
STEP 7: Continue adding rows until all new Cost Rate Rules and actual Rates have been added.
STEP 8: Click OK when done