Print Productivity Reports


There are 4 different reports available with information to understand how you are tracking on the project:




Run the Weekly Production Input Sheet after entering your quantities. Give this to your field person who is collecting what is being completed in the field.

The Phase Quantity Report, Phase Yield Report, and Project Labour Report (CMiC is from Canada) are all used to view productivity after quantities are entered on the job. These reports are run for the week.

NOTE: Best to wait until after your labor posts for the week, before running these or the quantities and labor won't match up.

The Field Productivity Report is run with a starting date each time of when the project first started to the current date of the last payroll posting.  This report will give you a whole project view of how you are doing for each phase code that is marked as "P" for Productivity.