CMiC R12 Project Status Report (PSR) known issues
Known Issue:
Box 1 - On some projects the PSR is not pulling in the Unposted External PCI's and the order of the rows appears to be rearranged. THIS ONE APPEARS TO BE FIXED
Box 1 - On other projects the PSR appears to be doubling the Unposted Internal PCI's and the order of the rows appears to be rearranged.
The fix for one issue appears to have created another depending on the project.
Box 7 - Fee is not calculating correctly
Workaround:
Print your Job Forecast Statement by Category report and verify against the Contract Forecasting screen. If accurate, submit the report along with your PSR. If NOT accurate, provide the Revenue and Fee #s from the screen to your Financial Manager.
If Job Forecast statement is also not accurate, submit the #s from the screen: