Construction KPI 2.0 - Project Dashboard App (More Coming Soon)
Budget (Allowance / Contingency / Buyout)

A
Allowance Remaining
Original Budget Allowance (Cost Status Query) - Current Budget (Cost Status Query) - Only filtering for 71180 (Live Data)
B
Contingency Remaining
Original Budget Contingency (Cost Status Query) - Current Budget (Cost Status Query) - Only filtering for 71190 (Live Data)
C
Buyout % Complete
Spent/Commitment (Filtering on 71140, 71145) / Cost Forecast (Forecast)
D
Allowance Variance %
Allowance % Used (Cost Status Query) - Cost % Complete (Forecast) - Filtering on 71180
E
Contingency Variance %
Contingency % Used (Cost Status Query) - Cost % Complete (Forecast) - Filtering on 71190
F
Buyout % Complete
Spent/Commitment (Filtering on 71140, 71145) / Cost Forecast (Forecast)